Grupotec adds 46MW of grid-connected PV in nine weeks

Related Companies

  • Grupotec's UK solar park

    Grupotec built and connected 12 PV projects with a total capacity of 46MW in just nine weeks. Image credit: Grupotec.

Grupotec, an investor in renewable energy projects, has announced it has connected 12 PV projects with a total capacity of 46MW to the grid in just nine weeks.

The 12 projects — which are located across the southwest of England on an approximate surface area of one million square meters — required a total investment of £50 million.

During the construction of the projects, Grupotec hired 500 workers and outsourced to 27 subcontractors. The works started on 15 January while the projects connected to the grid on 31 March.

The projects are composed of more than 180,000 solar panels, 1.3 million metres of cabling and over 2,000 tons of steel framework. Together, they are expected to produce around 38 million kWh of electricity every year.

Including these latest projects, Grupotec UK has a total installed PV capacity of 60MW.

Newsletter

We won't share your details - promise!

Preview Latest

Solar Business Focus UK »

The must-have UK solar installer magazine.
Subscribe today!

Only £60 for five editions sticker
Solar Business Focus UK Magazine Cover

Latest MCS Products »

  • Ground Source Heat Pump
    OCHSNER Warmepumpen

    GMSW 7 plus, GMSW 10 plus, GMSW 10 plus S, GMSW 15 plus and GMSW 17 plus ground source units

    Certificate: BBA 0037/1
  • Ground Source Heat Pump
    OCHSNER Warmepumpen

    GMSW 7 plus, GMSW 10 plus, GMSW 10 plus S, GMSW 15 plus and GMSW 17 plus ground source units

    Certificate: BBA0037/2
  • Solar Photovoltaic
    Solaria Energia Y Medio Ambiente S.A.

    S5M150W to S5M185W with increment of five S6P195W to S6P240W with increment of five S6M195W to S6M245W with increment of five S6M2G195W to S6M2G245W in increments of five

    Certificate: BBA0040