cleve hill

July 10, 2024
The developer of Cleve Hill Solar Park, a 373MW solar farm, has successfully appealed Swale Council’s decision to refuse consent for the co-located 150MW battery energy storage system (BESS).
March 11, 2024
Cleve Hill Solar Park has confirmed that Swale Borough Council’s planning committee refused the proposed BSMP for the project.
March 1, 2024
A local planning committee for Swale Borough Council has refused the battery storage application for the 373MW Cleve Hill Solar Park.
October 9, 2023
Greek-based Mytilineos Energy and Metals has signed an EPC contract for the 373MW Cleve Hill solar project.
May 24, 2023
When people in the industry discuss large-scale solar projects in the UK several names come to mind, but perhaps the most influential of all is Cleve Hill Solar Park.
September 3, 2021
BayWa r.e. is planning the development of a 163MW solar project in South Derbyshire.
July 14, 2020
Cleve Hill Solar Park has dodged an attempt to get its development consent overturned by Swale Borough Council.
June 1, 2020
Following the approval of Cleve Hill Solar Park, Solar Power Portal takes a look at what the next steps are for the project, any technology concerns and whether this will be the first of many Nationally Significant solar infrastructure projects.
May 28, 2020
Cleve Hill Solar Park, set to be the largest in the UK, has been granted development consent by the energy secretary.
March 3, 2020
The planning inspectorate has submitted its recommendations for the controversial Cleve Hill Solar Park, which is set to be Britain’s biggest solar farm.

Email Newsletter

Upcoming Events

22 October 2024
New York, USA
13 November 2024
Barcelona, Spain
21 November 2024
London, UK
26 November 2024
Malaga, Spain
26 November 2024
Warsaw, Poland

You are now subscribed!

Thank you for subscribing to the email newsletter. You can opt-out at any time.